What an Edina Teardown Actually Costs (and Where the Money Goes)
The number before the number: what it takes to clear a lot and start new in Edina.
You have found the right street in Edina. The house on it is not the right house. Maybe the ceilings are low, the foundation is tired, or the layout fights the way your family lives. The question is no longer whether to build new. It is what it will really cost to take the old house down and put the right one in its place.
Most cost conversations skip the first layer: the money spent before a single new wall goes up. This is that layer, in plain numbers, from a builder who is doing it right now on Mildred Avenue.
The first number: getting to a clean lot
In Edina, plan on roughly $25,000 to $35,000 to get from an existing house to a buildable lot. That covers demolition and hauling, disconnecting and capping utilities, and the city fees that come with removing a house. It does not include the new home itself.
Older Edina homes can also hold asbestos or lead paint. David is a licensed asbestos inspector and EPA Lead-Safe certified, so suspect materials are identified and tested before anything is disturbed. If abatement is needed, it is priced and approved before demolition begins.
The second number: the new home
Most of our custom homes fall between $600 and $900 per square foot, depending on site, size and finishes. Where a home lands in that range is decided by design and selections: the stone, the windows, the millwork, the kitchen. We price those choices as they are made, so the number grows up with the drawings instead of arriving as a surprise.
We work open-book on a cost-plus basis: you see the actual cost of the work, plus a builder fee and a design-studio fee stated from the start. Allowances are limited to light fixtures and plumbing fixtures, and every change is written, priced and approved before it proceeds.
The third number: time
Time is a cost too. We give a timeline once the permit is pulled. From that day, construction runs six to fourteen months, depending on size and selections.
In Edina the city reviews new homes closely, including height, setbacks, grading and trees, so we confirm the rules for your specific lot before design is fixed. A plan that fits the lot from the start does not lose months in review.
When a teardown is the right call
A teardown makes sense when the existing structure cannot become the house you want without being rebuilt anyway: a failing or shallow foundation, low ceilings the structure cannot raise, or systems that would all need replacing. In those cases a renovation becomes a new house wearing an old shell, and it should be priced as one.
It is not always the answer. On Walnut Drive in Edina, the owners kept their house and transformed it with a second-story addition, a new roof and a whole-home remodel in about eight months. The right choice depends on what the existing house gives you.
A current example: Mildred Avenue
On Mildred Avenue in Edina, an older house stood on the lot. We took it down and are building a new custom home in its place. Framing is underway now, and the home is scheduled to be finished in spring 2027. You can follow its progress on the project page. See the progress
Decision framework
- Budget roughly $25,000 to $35,000 to clear an Edina lot before construction
- Test for asbestos and lead before demolition, and price any abatement
- Plan $600 to $900 per square foot for the new home, driven by design and selections
- Expect a written schedule once the permit is pulled; construction then runs six to fourteen months
- Confirm the city rules for your lot before design is fixed
- Compare against a renovation honestly before deciding to tear down
Frequently asked questions
How much does it cost to tear down a house in Edina?
Roughly $25,000 to $35,000 for demolition, utility disconnects and city fees, before any new construction begins.
How much does it cost to build a new custom home in Edina?
Most of our custom homes fall between $600 and $900 per square foot, depending on site, size and finishes.
How long does an Edina teardown and rebuild take?
We give a timeline once the permit is pulled. From that day, construction runs six to fourteen months, depending on size and selections.
Do you test for asbestos before demolition?
Yes. David is a licensed asbestos inspector and EPA Lead-Safe certified, so suspect materials are identified and tested before anything is disturbed.
Next step
If you are weighing a teardown in Edina, we can walk the lot with you and give you the real numbers, from demolition to keys, before you decide anything.